SACRAMENTO, Calif. (FOX26) — Earlier this year we looked at the latest information that provided an update at the time.
According to the website's latest numbers as of April of this year, the project was 55% finished.
Specifically, about 95% of the exterior was done, but the plaza skylight is finished and the building is fully enclosed.
As far as the inside of it, framing was ongoing at the time with the electrical vault complete.
Their transition to temporary power started around that time as well.
Now in this latest check for an update, as of July, the transition from temporary power to permanent power between the capitol and the annex has been completed.
The building is now primarily weathertight, and interior drywall installation and mechanical, electrical, and plumbing work are underway.
State officials still believe that the project is on schedule to be completed by October of next year.
As of July, $668 million in total.
Those latest financial figures were provided by the construction company overseeing the project Gilbane.
According to the company's latest budget update in July of this year, the total amount of $1.19 billion is still the targeted amount that will be needed with no changes necessary.